How to trigger Listfind function
Hi all
If the form field is empty this code sets the variable nxtstep depending on the day of the week checking if the form field "is not date" and works fine in this case.
If the form field is not empty then it sets the variable nxtstep as the date that is selected which it does, however, it is not checking to see if it is a holiday. It should trigger the listfind function and check to see if the entered date is a holiday but it is just entering the date without going through this check.
Why is this not working? Thank you
<!--- UPDATE QUERY --->
<cfif isDefined("form.UPDATEADDBTN")>
<cfif FORM.ENTID GTE 1>
<cfset isCOMPANYNull = iif(len(trim(form.COMPANY)) EQ 0, true, false)>
<cfset isCOMMENTSNull = iif(len(trim(form.COMMENTS)) EQ 0, true, false)>
<!--- SET DATE AS FORM FIELD --->
<cfset nxtstep = trim(form.ABUNDANCE)>
<!--- SET DATE IF NO DATE ENTERED --->
<cfif not isDate(nxtstep)>
<cfif DayOfWeek(Now()) eq 2>
<cfset nxtstep = dateAdd("d", 2, now())>
<cfelseif DayOfWeek(Now()) eq 3>
<cfset nxtstep = dateAdd("d", 2, now())>
<cfelseif DayOfWeek(Now()) eq 4>
<cfset nxtstep = dateAdd("d", 2, now())>
<cfelseif DayOfWeek(Now()) eq 5>
<cfset nxtstep = dateAdd("d", 4, now())>
<cfelseif DayOfWeek(Now()) eq 6>
<cfset nxtstep = dateAdd("d", 3, now())>
<cfelseif DayOfWeek(Now()) eq 7>
<cfset nxtstep = dateAdd("d", 2, now())>
<cfelseif DayOfWeek(Now()) eq 1>
<cfset nxtstep = dateAdd("d", 1, now())>
</cfif>
<!--- IF A DATE IS ENTERED CHECK TO SEE IF IT IS A HOLIDAY --->
<cfelse>
<!--- CHECK TO SEE IF ENTERED DATE IS A HOLIDAY AND ADD DAYS--->
<cfif ListFind(ValueList(hols.holiday), nxtstep)>
<cfif DayOfWeek(nxtstep) eq 2>
<cfset nxtstep = dateAdd("d", 2, nxtstep)>
<cfelseif DayOfWeek(nxtstep) eq 3>
<cfset nxtstep = dateAdd("d", 5, nxtstep)>
<cfelseif DayOfWeek(nxtstep) eq 4>
<cfset nxtstep = dateAdd("d", 2, nxtstep)>
<cfelseif DayOfWeek(nxtstep) eq 5>
<cfset nxtstep = dateAdd("d", 4, nxtstep)>
<cfelseif DayOfWeek(nxtstep) eq 6>
<cfset nxtstep = dateAdd("d", 6, nxtstep)>
<cfelseif DayOfWeek(nxtstep) eq 7>
<cfset nxtstep = dateAdd("d", 2, nxtstep)>
<cfelseif DayOfWeek(nxtstep) eq 1>
<cfset nxtstep = dateAdd("d", 1, nxtstep)>
</cfif>
</cfif>
</cfif>