Hi-

I am hoping this is an easy answer. I have been instructed to time my sequences which have been edited in 23.98 as 29.97. Do i simply drop my 23.98 sequence into a 29.97 sequence and use that time?...Or is there some sort of calculator that can do this?

This topic has been closed for replies.

1 reply

R Neil Haugen
Legend
February 10, 2021

Duplicate the sequence, then in the dupe, change the frame-rate in Sequence settings, and see what you get.

 

Going one way between them needs a "3:2 pulldown" and going the other way isn't nearly so difficult to get looking/timed decently. I always forget which is which. I think going 29.97->23.976 is the problem one.

 

Any way, give it a shot and see what happens. Fastest way to check.

 

Neil